Possession-to-move-in planner

Pick your handover date and see a realistic week-by-week plan to move in, with a calendar file that reminds you the day before each stage starts.

Estimated move-in (about 18 weeks)
17 Feb 2027
1. Snag inspection and builder fixesUse the snag checklist; get issues acknowledged in writing.12 Oct 2026 – 19 Oct 2026
2. Shortlist designers and share your briefMeet 2–3 designers; compare itemised BOQs.20 Oct 2026 – 30 Oct 2026
3. Design finalisation and BOQ sign-offFreeze layout, materials and payment milestones before work starts.31 Oct 2026 – 16 Nov 2026
4. Orders and approvals (society permission, material lead times)Place orders for long-lead items such as tiles, fittings and hardware.17 Nov 2026 – 24 Nov 2026
5. Civil, electrical and plumbing workCheck concealed work and take photos before walls are closed.25 Nov 2026 – 11 Dec 2026
6. False ceiling and wall preparationConfirm light positions and cove details.12 Dec 2026 – 23 Dec 2026
7. Carpentry and modular installationInspect the first installed unit closely before the rest follow.24 Dec 2026 – 21 Jan 2027
8. Flooring finishing, painting and polishingApprove shade samples on the wall first.22 Jan 2027 – 04 Feb 2027
9. Lighting, fixtures and deep cleanKeep appliance and fixture warranty cards together.05 Feb 2027 – 11 Feb 2027
10. Final snag and move-inWalk through with your designer; agree handover documents.12 Feb 2027 – 17 Feb 2027

A typical 3BHK turnkey sequence with Sundays off. Real timelines depend on scope, society permissions, material lead times and your designer's schedule. Keep a buffer.